Ingrid tunnel - Velbert, Germany

The Project:


Extension of the L433 road Velbert/Langenberg


Executing company:

Wayss & Freytag Ing. Bau AG


The Problem:


The ground water must be pumped off. Continuous truck traffic has to be ensured due to the traditional excavation by means of building machines, i.e. pollution by mud must be prevented by continuously pumping off in pumping on snore mode.


Our Solution:


Lowering the ground water table by means of contractors' pumps of the KTZ and KTV series. Our pumps are provided with an inhouse developed oil lifter which ensures lubrication and cooling of the mechanical seal even at a minimum oil level.

Twenty-four-hour pumping on snore mode without failure has been implemented for months now due to this particular feature.

Download

Aşındırıcı ve korosif kullanım durumunda, belirli parçalarda doğal olarak daha ciddi yıpranma ve aşınma meydana gelecektir. Yukarıdaki bahsedilen tipte uygulama söz konusu olursa pervane, karıştırıcı, emme plakası, şaft kovanı, yağ segmanı, mekanik conta, pompa gövdesi, filtre elemanı, motor karteri ve tahliye bağlantısında yıpranma ve aşınma meydana gelebilir. Çalışma koşullarına bağlı olarak bu parçaların kullanım ömrü ciddi oranda farklılık gösterebilir ve yasal garanti süresinden kısa olabilir.
Bu anlamda lütfen talep ettiğinizde size de gönderdiğimiz genel hüküm ve koşullar belgemizi inceleyin.