ICE railway track Airport Cologne-Bonn

The project:


Underground railway track for linking Cologne-Bonn airport


Executing companies:

Consortium Flughafenanbindung

Köln/Bonn Los3

E. Heitkamp GmbH

Wayss & Freytag Ingenieurbau GmbH

Bauer Spezialtiefbau GmbH

F.C. Trapp AG

Dewatering with 24-h pump duty by:

Smet GWT N.V., Dessel, Belgium

Biergans Pumpen-Vertrieb GmbH, Duisburg


The problem:


Pumping off the water arising during underground tunnel heading, lowering the ground water level over a large area.


Our solution:


Deep wells were built in the area in which submersible waste water pump were installed. This allowed to lower the ground-water table to the lowest possible level.

Download

Tunel entrance Hermann-Lönsstraße, 1st section of excavation.
Aşındırıcı ve korosif kullanım durumunda, belirli parçalarda doğal olarak daha ciddi yıpranma ve aşınma meydana gelecektir. Yukarıdaki bahsedilen tipte uygulama söz konusu olursa pervane, karıştırıcı, emme plakası, şaft kovanı, yağ segmanı, mekanik conta, pompa gövdesi, filtre elemanı, motor karteri ve tahliye bağlantısında yıpranma ve aşınma meydana gelebilir. Çalışma koşullarına bağlı olarak bu parçaların kullanım ömrü ciddi oranda farklılık gösterebilir ve yasal garanti süresinden kısa olabilir.