The Project:


Dülmen canal construction - micro tunneling, Germany


Executing company:

Fa. Jordan Tiefbau GmbH & Co. KG

Kierdorfer Str. 65

D-50169 Kerpen


The Problem:


The soil loosened at the fron when heading is returned to the pressing pit and must be removed here and disposed.


Our Solution:


The viscous concentrated soil could be sucked off ba a KTZ pump with "suction hat" (reversed inlet strainer).

The specific advantage was the operation of the pump which could be used also during pressing. Transporting off was simple as it was possible to pump the drilling material directly into the containers provided.

No tank truck was necessary.

Download

Aşındırıcı ve korosif kullanım durumunda, belirli parçalarda doğal olarak daha ciddi yıpranma ve aşınma meydana gelecektir. Yukarıdaki bahsedilen tipte uygulama söz konusu olursa pervane, karıştırıcı, emme plakası, şaft kovanı, yağ segmanı, mekanik conta, pompa gövdesi, filtre elemanı, motor karteri ve tahliye bağlantısında yıpranma ve aşınma meydana gelebilir. Çalışma koşullarına bağlı olarak bu parçaların kullanım ömrü ciddi oranda farklılık gösterebilir ve yasal garanti süresinden kısa olabilir.