Direkt zum Inhalt | Direkt zur Navigation
Du är här:

Tunnel Siegkreisel, Betzdorf

The Project:


Construction of a 360 m long tunnel with three lanes as component of a municipal bypass system; completion: Spring, 2006.


Executing company:

ARGE Tunnel Tunnel Siegkreisel, Betzdorf

Hochtief Construction AG

Kirchner Bau GmbH

Alpine Bau Deutschland GmbH


The Problem:


Pumping off of the water arising during the underground tunnel heading.


Our Solution:


Use of submersible pumps of type KTZ32.2, these being operated in permanent snore mode (dry running) during the complete construction period. This application is no problem for the pump thanks to the inhouse developed oil distributor in combination with the rotating mechanical seal, which is located completely internally.

I händelse av nötande och korrosivt nyttjande uppstår större naturligt slitage i vissa komponenter. Med hänsyn till tillämpningen ovan kan slitage främst förekomma i pumphjul, omrörare, sugplatta, axelhylsa, oljering, mekanisk tätning, pumphölje, sil, motorhölje och utloppskoppling. Beroende på arbetsvillkoren kan livslängden för dessa delar variera kraftigt och vara kortare än den lagstadgade garantiperioden.
I det avseendet, vänligen uppmärksamma våra allmänna villkor som vi också skickar till dig via e-post på begäran.