The Project:


Pipe heading DN1200 Aakerfährstraße, Duisburg, Germany

Executing company:

Siebert Bauunternehmung GmbH, Bebra



The Problem:


Lowering and maintaining the groundwater table. At the beginning several medium-sized pumps were employed which burdened the mains electricity supply excessively. As the river Rhine flows past at a distance of 200m the groundwater could only be lowered with difficulty.


Our Solution:


A pump of type KRS2-89 incl. hosepipe and 300m drainage in the form of a pipe. Draining of the excavation for the whole construction period. Operation of the pump in 24-hour pumping on snore mode.

Download

U slučaju abrazivnog i korozivnog korišćenja, u nekim komponentama može doći do prirodnog habanja. U pogledu gornje primene do habanja može doći pre svega kod rotora, agitatora, usisne ploče, rukavca vratila, uljanog prstena, mehaničke zaptivke, kućišta pumpe, sita, kućišta motora i ispusne spojnice. Radni vek ovih delova može znatno da varira zavisno od radnih uslova i može biti kraći od garantnog perioda.
U tom smislu obratite pažnju na naše opšte uslove korišćenja koje vam takođe na zahtev šaljemo poštom.