The project:


Construction of a tunnel using caissons


Executing companies:

Skanska AS

Intec Pumper AS


The problem:


During construction of a tunnel with caissons, the individual elements had to be emptied after positioning. In addition, water flowing in along the segment had to be pumped out.


Our solution:


To pump larger quantities of water, pumps from the KTV series were used. Along the segment, model LSC pumps were installed. These flat suction pumps remove water above a residual level of 1mm, allowing work to proceed in as dry an environment as possible.

V prípade použitia v abrazívnom alebo korozívnom prostredí sa niektoré súčasti prirodzene opotrebujú rýchlejšie. S ohľadom na takúto aplikáciu sa opotrebenie môže týkať hlavne obežného kolesa, miešadla, sacej dosky, puzdra hriadeľa, olejového tesnenia, mechanického tesnenia, krytu čerpadla, sita, krtyu motora a spojky odtoku. V závislosti od pracovných podmienok sa životnosť týchto súčastí môže podstatne líšiť a byť kratšia než zákonná záručná doba.
Preto, prosím, vezmite do úvahy naše všeobecné zmluvné podmienky, ktoré vám na vyžiadanie zašleme poštou.