Lainz Tunnel, contract section LT31, Austria

The Project:


Construction of a 4km two-track railway tunnel in Vienna


Executing companies:

ARGE LT31 consisting of:

Hochtief Construction AG

Alpine Bau GmbH

Beton- und Monierbau GmbH


The problem:


Water removal from both tunnel tubes during tunnelling works (through loose rock). 5 emergency exit shafts, 30 to 55m deep. Quarrying areas 132 and 145 m2, 6 to 20m beneath existing buildings.


The solution:


Multiple submersible pumps from the KTV, KTZ and LH series. The special characteristics of Tsurumi pumps,such as an internal mechanical seal, upstream shaft sleeve with gasket and an oil lifter allow them to be used in on-snore-mode over an extended period.

V prípade použitia v abrazívnom alebo korozívnom prostredí sa niektoré súčasti prirodzene opotrebujú rýchlejšie. S ohľadom na takúto aplikáciu sa opotrebenie môže týkať hlavne obežného kolesa, miešadla, sacej dosky, puzdra hriadeľa, olejového tesnenia, mechanického tesnenia, krytu čerpadla, sita, krtyu motora a spojky odtoku. V závislosti od pracovných podmienok sa životnosť týchto súčastí môže podstatne líšiť a byť kratšia než zákonná záručná doba.
Preto, prosím, vezmite do úvahy naše všeobecné zmluvné podmienky, ktoré vám na vyžiadanie zašleme poštou.