The project:
Deployment of TSURUMI wastewater pumps in the filtration plant
Executing companies:
Emschergenossenschaft
Biergans Pumpen-Vertriebs GmbH, Duisburg
The problem (1):
Feed pit of the filtration plant: The pump can become obstructed by blockages and then needs to be cleaned at length and recommissioned.
Our solution (1):
Supply and installation of a 100C43.7 with guide tubes and connection elbow (small pit, very little room for manoeuvre). This pump is equipped with cutters to prevent blockages.
The problem (2):
Overflow structure for media that are contaminated by chemicals.
Our solution (2):
Deployment of a corrosion-resistant 50SQ2.4S pump (0.4 kW) in stainless steel to pump the medium at the structure.