Ingrid tunnel - Velbert, Germany

The Project:


Extension of the L433 road Velbert/Langenberg


Executing company:

Wayss & Freytag Ing. Bau AG


The Problem:


The ground water must be pumped off. Continuous truck traffic has to be ensured due to the traditional excavation by means of building machines, i.e. pollution by mud must be prevented by continuously pumping off in pumping on snore mode.


Our Solution:


Lowering the ground water table by means of contractors' pumps of the KTZ and KTV series. Our pumps are provided with an inhouse developed oil lifter which ensures lubrication and cooling of the mechanical seal even at a minimum oil level.

Twenty-four-hour pumping on snore mode without failure has been implemented for months now due to this particular feature.

În cazul utilizării abrazive și corozive, se va produce o uzură mai puternică în mod normal la anumite componente. În ceea ce privește aplicația de mai sus, uzura se poate produce mai ales la rotor, agitator, placa de aspirație, manșonul arborelui, inelul de ulei, garnitura mecanică, carcasa pompei, filtru, carcasa motorului și cupla de descărcare. În funcție de condițiile de lucru, durata de viață a acestor componente poate varia semnificativ și poate fi mai scurtă decât perioada de garanție legală.
În acest sens, vă rugăm să citiți cu atenție termenii și condițiile noastre generale (www.tsurumi.eu/english/GCS.htm) pe care vi le putem trimite, la cerere, și prin poștă.