The project:


Construction of a tunnel using caissons


Executing companies:

Skanska AS

Intec Pumper AS


The problem:


During construction of a tunnel with caissons, the individual elements had to be emptied after positioning. In addition, water flowing in along the segment had to be pumped out.


Our solution:


To pump larger quantities of water, pumps from the KTV series were used. Along the segment, model LSC pumps were installed. These flat suction pumps remove water above a residual level of 1mm, allowing work to proceed in as dry an environment as possible.

În cazul utilizării abrazive și corozive, se va produce o uzură mai puternică în mod normal la anumite componente. În ceea ce privește aplicația de mai sus, uzura se poate produce mai ales la rotor, agitator, placa de aspirație, manșonul arborelui, inelul de ulei, garnitura mecanică, carcasa pompei, filtru, carcasa motorului și cupla de descărcare. În funcție de condițiile de lucru, durata de viață a acestor componente poate varia semnificativ și poate fi mai scurtă decât perioada de garanție legală.
În acest sens, vă rugăm să citiți cu atenție termenii și condițiile noastre generale (www.tsurumi.eu/english/GCS.htm) pe care vi le putem trimite, la cerere, și prin poștă.