Extension of connection road L639 in Gelsenkirchen

The Project:


Extension of the connection road L639,

Florastraße Gelsenkirchen

Executing company:

Heitkamp Erd- und Straßenbau GmbH


The Problem:


Repumping a mixed water channel because a shaft had to be installed.


Our Solution:


Two Tsurumi KRS822 pumped off the dammed water. 720 m³/h were re-passed into the mixed water channel at a distance of 100 m.


This took 3 weeks where the pumps were in service 24 h a day without any failure.


The pumps were laid into the bed of the channel without further installation. No problem for Tsurumi pumps.

No caso de uma utilização abrasiva e corrosiva, certos componentes sofrerão um desgaste natural. No que respeita à aplicação anterior, o desgaste pode decorrer sobretudo no impulsor, agitador, placa de sucção, manga do veio, anel de óleo, vedação mecânica, revestimento da bomba, filtro, revestimento do motor e acoplamento de descarga. Dependendo das condições de trabalho, a vida útil daquelas peças pode variar significativamente e pode ser mais reduzida do que o período legal da garantia.