The Project:


Remediation of a wastewater sewer, stormwater treatment SKO 405 Cologne


Executing company

F.C. Trapp Tief- und Straßenbau Köln GmbH


The Problem:


Pumping of the wastewater arising during the 8month construction period including complete construction and laying out of a DN 250 pressure line with a length of 1200 m including overpasses and transverse sections.


Our Solution:


Three wastewater pumps of type 100C411 with non-clog impeller with cutter were used. The special impeller comminutes solid matter that arises so that blockages cannot occur. Operational reliability held the highest priority here.

No caso de uma utilização abrasiva e corrosiva, certos componentes sofrerão um desgaste natural. No que respeita à aplicação anterior, o desgaste pode decorrer sobretudo no impulsor, agitador, placa de sucção, manga do veio, anel de óleo, vedação mecânica, revestimento da bomba, filtro, revestimento do motor e acoplamento de descarga. Dependendo das condições de trabalho, a vida útil daquelas peças pode variar significativamente e pode ser mais reduzida do que o período legal da garantia.
A este propósito, atente aos nossos termos e condições gerais que também lhe enviamos por email, se solicitado.