Schwarzbach pipe heading, Germany

The Project:


Gelsenkirchen pipe heading, Schwarzbach canal, Germany

Executing company: WÜWA Bau GmbH


The Problem:


The material excavated by the micro-tunnelling machine is pumped by a mud pump into a separating system where coarse parts are separated. The remaining highly abrasive sludge is passed into a receiver. The material deposits due to the intermittent operation of the pump.


Our Solution:


A KRS2-80 with agitator whirls up the abrasive sludge so that it can be pumped off without any problem. Minimum wear is possible due to the application of components of grey cast and chromium cast iron (25% chromium portion).

In het geval van schurend en corrosief gebruik, zullen bepaalde componenten van nature sneller verslijten. Met betrekking tot bovenstaande toepassing kan slijtage met name optreden in de waaier, de roerder, het zuigdeksel, de asbus, de oliering, de mechanische asafdichting,het pomphuis, de zuigkorf, de motorbehuizing en de afvoerkoppeling. Afhankelijk van de werkingsomstandigheden kan de levensduur van die onderdelen aanzienlijk variëren en kan deze korter zijn dan de wettelijke garantieperiode.
Gelieve in dit verband rekening te houden met onze algemene voorwaarden, die we u op aanvraag kunnen toesturen.