Nibelungen Bridge Worms, Germany

The project:


New building of second Rhine Bridge


Executing company:

Max Bögl Bauunternehmung GmbH & Co. KG


The new bridge project, built 36 metres away from the old bridge, is a total of 745 metres in length. The section over the Rheinstrom is 322 metres long.


The problem:


Pumping off the water and concrete mixture created in the course of boring piles that are 900mm in diameter at a depth of up to 50m into the ground for soil stabilization.


Our solution:


Use of a KTZ411 Tsurumi pump for securing the boring piles during the casting phase. The unit is used to pump out the mixture of water and concrete.

In het geval van schurend en corrosief gebruik, zullen bepaalde componenten van nature sneller verslijten. Met betrekking tot bovenstaande toepassing kan slijtage met name optreden in de waaier, de roerder, het zuigdeksel, de asbus, de oliering, de mechanische asafdichting,het pomphuis, de zuigkorf, de motorbehuizing en de afvoerkoppeling. Afhankelijk van de werkingsomstandigheden kan de levensduur van die onderdelen aanzienlijk variëren en kan deze korter zijn dan de wettelijke garantieperiode.