The project:


Construction of a tunnel using caissons


Executing companies:

Skanska AS

Intec Pumper AS


The problem:


During construction of a tunnel with caissons, the individual elements had to be emptied after positioning. In addition, water flowing in along the segment had to be pumped out.


Our solution:


To pump larger quantities of water, pumps from the KTV series were used. Along the segment, model LSC pumps were installed. These flat suction pumps remove water above a residual level of 1mm, allowing work to proceed in as dry an environment as possible.

In het geval van schurend en corrosief gebruik, zullen bepaalde componenten van nature sneller verslijten. Met betrekking tot bovenstaande toepassing kan slijtage met name optreden in de waaier, de roerder, het zuigdeksel, de asbus, de oliering, de mechanische asafdichting,het pomphuis, de zuigkorf, de motorbehuizing en de afvoerkoppeling. Afhankelijk van de werkingsomstandigheden kan de levensduur van die onderdelen aanzienlijk variëren en kan deze korter zijn dan de wettelijke garantieperiode.
Gelieve in dit verband rekening te houden met onze algemene voorwaarden, die we u op aanvraag kunnen toesturen.