Pipe heading Aakerfährstraße, Germany

The Project:


Pipe heading DN1200 Aakerfährstraße, Duisburg, Germany

Executing company:

Siebert Bauunternehmung GmbH, Bebra



The Problem:


Lowering and maintaining the groundwater table. At the beginning several medium-sized pumps were employed which burdened the mains electricity supply excessively. As the river Rhine flows past at a distance of 200m the groundwater could only be lowered with difficulty.


Our Solution:


A pump of type KRS2-89 incl. hosepipe and 300m drainage in the form of a pipe. Draining of the excavation for the whole construction period. Operation of the pump in 24-hour pumping on snore mode.

In caso di utilizzo di prodotti abrasivi o corrosivi, alcuni componenti saranno naturalmente soggetti a maggiore usura. Riguardo alla suddetta applicazione, l'usura può avvenire principalmente nella girante, nell'agitatore, nella piastra aspirante, nel manicotto dell'albero, nell'anello di lubrificazione, nella tenuta meccanica, nel corpo della pompa, nel filtro, nel corpo del motore e nel raccordo di scarico. A seconda delle condizioni di lavoro, la durata di queste parti può variare significativamente ed essere inferiore al periodo legale di garanzia.
A questo proposito, si prega di prestare attenzione ai nostri termini e condizioni generali, che possiamo anche inviare per posta elettronica su richiesta.