The Project:


Underground railway track to link the Cologne-Bonn airport, Germany

Executing companies:

Consortium Airport tunnel Cologne-Bonn lot 3

Wayss & Freytag Ingenieurbau AG,

E. Heitkamp GmbH, F.C. Trapp AGComplete dewatering (24h-duty) carried out by:

Smet GWT N.V., Dessel, Belgien

Biergans Pumpen-Vertrieb GmbH, Duisburg



The Problem:


Open dewatering by means of submersible pumps.


Our Solution:


The groundwater generated is pumped off by several submersible pumps for abrasive water. 24-h on-snore-operation must be ensured. Currently a total of twenty KTZ21.5 and ten KTZ32.2 is in operation.

U slučaju abrazivnih i korozivnih primjena, normalno je da će se u određenim komponentama dogoditi snažnije trošenje. S obzirom na gornju primjenu trošenje se može odvijati uglavnom u radnom kolu, miješalici, usisnoj ploči, rukavcu osovine, uljnom prstenu, mehaničkoj brtvi, kućištu pumpe, cjedilu, kućištu motora i ispusnoj spojki. Ovisno o radnim uvjetima vijek trajanja tih dijelova može značajno varirati i može biti kraći od pravnog zakonskog razdoblja.