Groundwater tanks on B23 Saulgrub, Germany

The project:

City bypass for federal road B23 - 450m groundwater tank through the Saulgrub upland moor between Saulgrub and Unterammergau.


Executing company:

HOCHTIEF Infrastructure GmbH, Southeast Germany branch


Tsurumi consultants:

Mr. Christian Kulik (External sales force Bavaria)


The problem:

During implementation of the Saulgrub bypass, a 450m seciond of federal road B23 had to be taken through an underpass under the Murnau-Oberammergau railway. The area is permanently underwater, and ground and strata water also entered. Water retention using well pumps is essential.


The solution:

Open water retention using small, single-phase model HS2.75S wastewater pumps, controlled by float switches. Three-phase model KTV2-15 and KTV2-22 wastewater pumps run in 24-hour sip operation.

En cas d'utilisation abrasive et corrosive, une usure plus important se manifestera naturellement dans certains composants. En rapport avec l'application ci-dessus, l'usure peut principalement apparaître au niveau de la turbine, de l'agitateur, du panneau d'aspiration, de la chemise d'arbre, de la bague de graissage, du joint mécanique, du carter de la pompe, du filtre, du carter du moteur et du couple de décharge. Selon les conditions de travail, la durée de vie de ces pièces peut varier de manière significative et peut être inférieure à la période légale de garantie.