The Project:


New construction of the MUCEM (Museum of European and Mediterranean Civilizations) in Marseille, France, on an area of 26,000 m3.


Company involved:

Messrs. Dumez Mediterranée (VINCI Group)

Construction Manager: Mr. Francis Berny


The Problem:


The site is located in the immediate vicinity of the Mediterranean coast and the Old Harbour of Marseille. In the first construction phase, a square pit was excavated, with an edge length of 72 m. From a depth of 6 m seawater began to infiltrate, and flooded the excavation.


The Solution:


In the first phase, dirty water pumps were used, of the types KTZ31.5, KTZ21.5 and KRS2-80. Settling basins were then installed, each with a pump of the type KTZ33.7, with plastic piping and switchboxes.


The KTZ pumps will be running until the site has been completed, and the settling basin allows for the continuous purification of the dirty water.

En el caso de utilizarse con productos abrasivos y corrosivos, determinados componentes sufrirán un desgaste más intenso de forma natural. En relación con la aplicación indicada más arriba, dicho desgaste se puede producir principalmente en el impulsor, el agitador, la placa de succión, el casquillo del eje, el anillo de engrase, el sello mecánico, la carcasa de la bomba, el colador, la carcasa del motor y el acoplamiento de descarga. En función de las condiciones de trabajo, la vida útil de estas piezas puede variar significativamente y puede ser inferior al período de garantía legal.
En este sentido, son de aplicación nuestros términos y condiciones generales, que también le podemos enviar por correo electrónico si lo solicita.