Reitersberg Tunnel, Germany

The Project:

Reitersberg Tunnel of the Ebensfeld–Erfurt ICE rail link


Contractor:

Alfred Kunz Untertagebau

Swietelsky Tunnelbau

Leonhard Weiss


Tsurumi support:

Christian Kulik (Field Sales)


The Problem:

The 2975 m long tunnel is being cut using mining methods. After the snow melted, the water incidence in the tunnel suddenly rose to a maximum of 20 litres/second. The medium was made highly abrasive by its slurried stone content.


The Solution:

Massive drainage pump of types KTZ411 and KTZ611 (11kW) transport water over a distance of 500m to 1000m. The KTZ series is the perfect contractors' pump due to its good performance. The replacement of wearing parts is very simple. After training by qualified Tsurumi staff, all maintenance can be done independently on site.


Aplinkoje, kur yra braižančių dalelių ir korozinių medžiagų, tam tikri komponentai natūraliai dėvisi greičiau. Eksploatuojant pirmiau minėtomis sąlygomis, sparčiau dėvisi sparnuotė, maišytuvas, siurbimo plokštė, veleno sandariklis, alyvos žiedas, mechaninis sandariklis, siurblio korpusas, koštuvas, variklio korpusas ir išleidimo mova. Atsižvelgiant į darbines sąlygas, šių dalių eksploatacija gali gerokai sutrumpėti ir nesiekti įstatymais nustatyto garantijos laikotarpio.
Tokiu atveju reikia atidžiai perskaityti mūsų bendrąsias sąlygas ir nuostatus, kuriuos, gavę atskirą užklausą, galime išsiųsti paštu.