Syphon construction under nature reserve Löcknitztal by microtunnelling

The project:


Pipe heading DN 1600 by micro-tunnelling with reinforced concrete driving pipes for passing under the nature reserve Löcknitztal near Kienbaum (Land Brandenburg) as protective pipe for a high-pressure gas pipeline DN 1100.

Client:

Ruhrgas AG/Verbundnetz Gas AG

Executing company:

Gildemeister Tief-, Stahlbeton- und

Rohrleitungsbau GmbH&Co. KG Berlin


The problem:


Pumping off the supporting liquid (bentonite suspension) used in the tunnel during pipe heading.


Our solution:


Application of a submersible pump Type KTZ35.5 connected with an accompanying pipe line DN 100 for continuous removal of the supporting liquid during the whole time of pipe heading.

The pump was always positioned at the lowest point of the syphon and operated on snore mode.

Σε περίπτωση χρήσης λειαντικού ή διαβρωτικού μέσου, μπορεί να προκληθεί μεγάλη φθορά σε ορισμένα εξαρτήματα. Αναφορικά με την παραπάνω εφαρμογή, μπορεί να προκληθεί φθορά κυρίως στην πτερωτή, στον αναδευτήρα, στην πλάκα αναρρόφησης, στο χιτώνιο ολίσθησης του άξονα, στον δακτύλιο λίπανσης, στo μηχανικό στεγανωτικό παρέμβυσμα, στο περίβλημα της αντλίας, στο φίλτρο, στο κιβώτιο του κινητήρα και στον άξονα σύζευξης του συστήματος αποστράγγισης. Η διάρκεια ζωής αυτών των εξαρτημάτων μπορεί να διαφέρει σημαντικά και μπορεί να είναι συντομότερη από εκείνη της περιόδου της εγγύησης κατά τον νόμο, εξαρτάται από τις συνθήκες εργασίας.