The project:

Mining of fluorspar and heavy spar in a newly activated mine.


Company carrying out the works:

Erzgerbirgische Fluss- und Schwerspatwerke GmbH, Oberwiesenthal, Germany


Subcontractor:

Bau Punkt Kraatz GmbH & Co.KG, Annaberg-Buchholz


Tsurumi supervisor:

Mr. Thomas Elendt (Field Sales Team East)


The problem:

Water penetrates the top of the mining shaft, washing away many sediments with a diameter of 0.1 mm to 0.2 mm. Both pumps and hoses quickly wear out under these conditions; the previous pumps had to be replaced approx. every six months.


The solution:

A Tsurumi type KTV2-22 construction pump, with a special pump housing made of PU rubber in 80A shore hardness, used in 24-hour continuous operations. The oldest pump of this kind operated continuously for 2.5 years without intensive maintenance. After an overhaul, only the mechanical seal, impeller, and the shaft protection housing, had to be exchanged.

I tilfælde af slibende og ætsende anvendelse vil stærkere slitage forekomme naturligt i visse komponenter. Med hensyn til ovenstående anvendelse kan slitage hovedsageligt finde sted i pumpehjul, omrørerenhed, sugeplade, akselhylster, oliering, mekanisk tætning, pumpehus, si, motorhus og udløbskobling. Afhængigt af arbejdsvilkårene kan levetiden for disse dele variere betydeligt og kan være kortere end den lovlige garantiperiode.