The Project:


Remediation of a wastewater sewer, stormwater treatment SKO 405 Cologne


Executing company

F.C. Trapp Tief- und Straßenbau Köln GmbH


The Problem:


Pumping of the wastewater arising during the 8month construction period including complete construction and laying out of a DN 250 pressure line with a length of 1200 m including overpasses and transverse sections.


Our Solution:


Three wastewater pumps of type 100C411 with non-clog impeller with cutter were used. The special impeller comminutes solid matter that arises so that blockages cannot occur. Operational reliability held the highest priority here.

I tilfælde af slibende og ætsende anvendelse vil stærkere slitage forekomme naturligt i visse komponenter. Med hensyn til ovenstående anvendelse kan slitage hovedsageligt finde sted i pumpehjul, omrørerenhed, sugeplade, akselhylster, oliering, mekanisk tætning, pumpehus, si, motorhus og udløbskobling. Afhængigt af arbejdsvilkårene kan levetiden for disse dele variere betydeligt og kan være kortere end den lovlige garantiperiode.
I den forbindelse skal du være opmærksom på vores generelle vilkår og betingelser , som vi også sender til dig via mail på anmodning.