The project:

Mining of fluorspar and heavy spar in a newly activated mine.


Company carrying out the works:

Erzgerbirgische Fluss- und Schwerspatwerke GmbH, Oberwiesenthal, Germany


Subcontractor:

Bau Punkt Kraatz GmbH & Co.KG, Annaberg-Buchholz


Tsurumi supervisor:

Mr. Thomas Elendt (Field Sales Team East)


The problem:

Water penetrates the top of the mining shaft, washing away many sediments with a diameter of 0.1 mm to 0.2 mm. Both pumps and hoses quickly wear out under these conditions; the previous pumps had to be replaced approx. every six months.


The solution:

A Tsurumi type KTV2-22 construction pump, with a special pump housing made of PU rubber in 80A shore hardness, used in 24-hour continuous operations. The oldest pump of this kind operated continuously for 2.5 years without intensive maintenance. After an overhaul, only the mechanical seal, impeller, and the shaft protection housing, had to be exchanged.

V případě použití v abrazivním a korozivním prostředí dochází přirozeně k silnějšímu opotřebení určitých součástí. S ohledem na výše uvedené použití může opotřebení probíhat především v oběžném kole, míchadle, sací desce, hřídelovém pouzdře, olejovém kroužku, mechanickém těsnění, plášti čerpadla, sítu, skříni motoru a výtlačné spojce. V závislosti na pracovních podmínkách se životnost těchto částí může výrazně lišit a být kratší než zákonná záruční lhůta.