Direkt zum Inhalt | Direkt zur Navigation
Jste zde:

MUCEM, Marseille, France

The Project:


New construction of the MUCEM (Museum of European and Mediterranean Civilizations) in Marseille, France, on an area of 26,000 m3.


Company involved:

Messrs. Dumez Mediterranée (VINCI Group)

Construction Manager: Mr. Francis Berny


The Problem:


The site is located in the immediate vicinity of the Mediterranean coast and the Old Harbour of Marseille. In the first construction phase, a square pit was excavated, with an edge length of 72 m. From a depth of 6 m seawater began to infiltrate, and flooded the excavation.


The Solution:


In the first phase, dirty water pumps were used, of the types KTZ31.5, KTZ21.5 and KRS2-80. Settling basins were then installed, each with a pump of the type KTZ33.7, with plastic piping and switchboxes.


The KTZ pumps will be running until the site has been completed, and the settling basin allows for the continuous purification of the dirty water.

Download

V případě použití v abrazivním a korozivním prostředí dochází pochopitelně u některých komponentů k rychlejšímu opotřebení. S ohledem na výše uvedené aplikace může docházet k opotřebení zejména na oběžném kole, agitátoru, přísavné desce, hřídelové objímce, olejovém kroužku, mechanickém utěsnění, krytu čerpadla, sítku, krytu motoru a na spoji v místě pro uvolňování materiálu. V závislosti na pracovních podmínkách se může životnost těchto částí výrazně lišit. Může být kratší než doba zákonné záruky.
V tomto ohledu prosím věnujte pozornost našim všeobecným obchodním podmínkám, které vám můžeme na základě vyžádání zaslat poštou.