Direkt zum Inhalt | Direkt zur Navigation
Вие сте тук:

Pipe heading Aakerfährstraße, Germany

The Project:


Pipe heading DN1200 Aakerfährstraße, Duisburg, Germany

Executing company:

Siebert Bauunternehmung GmbH, Bebra



The Problem:


Lowering and maintaining the groundwater table. At the beginning several medium-sized pumps were employed which burdened the mains electricity supply excessively. As the river Rhine flows past at a distance of 200m the groundwater could only be lowered with difficulty.


Our Solution:


A pump of type KRS2-89 incl. hosepipe and 300m drainage in the form of a pipe. Draining of the excavation for the whole construction period. Operation of the pump in 24-hour pumping on snore mode.

В случай на утилизация на абразивни и корзивни материали, в определени компоненти естествено ще настъпи по-значително износване. По отношение на горепосоченото приложение, износването може да настъпи главно в импелер, агитатор, смукателна плоча, втулка на вала, маслен пръстен, механично уплътнение, корпус на помпата, филтър, корпус на двигателя и смукателен съединител. В зависимост от условията на работа, животът на тези части може да варира значително и може да бъде по-кратък от законовия гаранционен период.
В тази връзка, моля, обърнете внимание на нашите общи условия , които също ви изпратим по пощата при поискване.