Tunnel Siegkreisel, Betzdorf

The Project:


Construction of a 360 m long tunnel with three lanes as component of a municipal bypass system; completion: Spring, 2006.


Executing company:

ARGE Tunnel Tunnel Siegkreisel, Betzdorf

Hochtief Construction AG

Kirchner Bau GmbH

Alpine Bau Deutschland GmbH


The Problem:


Pumping off of the water arising during the underground tunnel heading.


Our Solution:


Use of submersible pumps of type KTZ32.2, these being operated in permanent snore mode (dry running) during the complete construction period. This application is no problem for the pump thanks to the patented oil distributor in combination with the rotating mechanical seal, which is located completely internally.

При употреба на абразивни и корозивни материали, в някои компоненти естествено ще се появи силно износване. Във връзка с по-горното приложение, износване ще възникне предимно в импелера, агитатора, засмукващата плоча, ръкава на вала, масления пръстен, механичното уплътнение, корпуса на помпата, цедката, корпуса на двигателя и смукателния куплунг. В зависимост от условията на работа на експлоатационният живот на официалния гаранционен срок.
В тази връзка, моля, обърнете внимание на нашите общи условия които ние също ще ви изпратим по пощата при поискване.