Tunnel project U3, Munich

The project:


Construction of underground tunnel line 3 North, lot 1

Execution companies:

Consortium U-Bahn Linie 3 Nord

Ed. Züblin AG, Ndl. Tunnelbau

Ed. Züblin AG, Ndl. München


The problem:


Pumping off the water arising during mined underground tunnel heading.


Our solution:


Use of 9 submersible waste water pumps of Type KTZ32.2.

Because of the highly calcareous water deposits occur in the pump hydraulics resulting in pump blocking. However, due to the mechanical seal positioned completely inside und the additional shaft protection sleeve with sealing ring the pump can be put quickly with little effort and without exchanging any wear parts back into operation again.

В случай на утилизация на абразивни и корзивни материали, в определени компоненти естествено ще настъпи по-значително износване. По отношение на горепосоченото приложение, износването може да настъпи главно в импелер, агитатор, смукателна плоча, втулка на вала, маслен пръстен, механично уплътнение, корпус на помпата, филтър, корпус на двигателя и смукателен съединител. В зависимост от условията на работа, животът на тези части може да варира значително и може да бъде по-кратък от законовия гаранционен период.
В тази връзка, моля, обърнете внимание на нашите общи условия , които също ви изпратим по пощата при поискване.