Bramschstraße tunnel - Dresden, Germany

The Project:


North-tangent Dresden-Gorbitz, Bramschstraße tunnel, Germany

Executing Company:

MAX BÖGL Group of companies

Postfach 1120

D-92310 Neumarkt

info@max-boegl.de

www.max-boegl.de


The Problem:


The tunnel lies in the ground water over its whole length. No free water table exists near the tunnel, the flow-in quantities depend on the distribution of the local flow quantities from top and vertical joints which extend as far as the main ground water course.


Our Solution:


KTZ35.5 is used in 24-hour pumping on snore mode. Because cement sludge and abrasive media are pumped here it is necessary to apply a highly wear resistant pump.

В случай на утилизация на абразивни и корзивни материали, в определени компоненти естествено ще настъпи по-значително износване. По отношение на горепосоченото приложение, износването може да настъпи главно в импелер, агитатор, смукателна плоча, втулка на вала, маслен пръстен, механично уплътнение, корпус на помпата, филтър, корпус на двигателя и смукателен съединител. В зависимост от условията на работа, животът на тези части може да варира значително и може да бъде по-кратък от законовия гаранционен период.
В тази връзка, моля, обърнете внимание на нашите общи условия , които също ви изпратим по пощата при поискване.