AZS ARGE Zugangsstollen, Linthal, Switzerland

The project:

Access shaft II -Kraftwerk Linth-Limmern AG "Project Linthal 2015"


Executing companies:

AZS ARGE Zugangsstollen

RL Pumpenanlagen GmbH, Wollerau


The problem:


Shafts with a pronounced tilt. drilling water and incoming water must be pumped out.


Our solution:


LH322W submersible pump is used, with a second pump held in reserve. The pump is frequency-controlled and regulated using a submersible pressure probe. If the water level rises, the speed is increased; when the water level falls, the speed is reduced. This type of control was chosen so that a very small pump container can be used which can be easily replaced after each new tunnel section. A model KTZ47.5 pump is built into the drainage water treatment.

В случай на утилизация на абразивни и корзивни материали, в определени компоненти естествено ще настъпи по-значително износване. По отношение на горепосоченото приложение, износването може да настъпи главно в импелер, агитатор, смукателна плоча, втулка на вала, маслен пръстен, механично уплътнение, корпус на помпата, филтър, корпус на двигателя и смукателен съединител. В зависимост от условията на работа, животът на тези части може да варира значително и може да бъде по-кратък от законовия гаранционен период.
В тази връзка, моля, обърнете внимание на нашите общи условия , които също ви изпратим по пощата при поискване.