Feldhofe mud dump site, Germany

The Project:


To treat the surface discharge water before it enters the receiving water course.


Executing company:

Firma PLA Pumpen und Anlagenbau GmbH

22844 Norderstedt


The problem:


The discharge water of the Feldhofe mud dumpsite is heavily laden with Fe-ions. Treatment of the surface discharge water is necessary before it enters the receiving watercourse.


The solution:


Treatment via oxidation and iron oxide precipitation, assisted by a 2.2kW submersible aerator. Since the bottom of the natural water body is uneven and muddy, a base plate was welded on and the aerator sunk using a crane. Oxygen measurements made after installation (using DO electrodes) were highly satisfactory.

При употреба на абразивни и корозивни материали, в някои компоненти естествено ще се появи силно износване. Във връзка с по-горното приложение, износване ще възникне предимно в импелера, агитатора, засмукващата плоча, ръкава на вала, масления пръстен, механичното уплътнение, корпуса на помпата, цедката, корпуса на двигателя и смукателния куплунг. В зависимост от условията на работа на експлоатационният живот на официалния гаранционен срок.
В тази връзка, моля, обърнете внимание на нашите общи условия които ние също ще ви изпратим по пощата при поискване.